| |
Wind Turbines |
|
| Introduction |
Fourteen wind turbines each up to 3MW are proposed
for the Chelveston airfield site. Each turbine will be
mounted on a tapered tubular steel tower supporting
the nacelle, hub and rotor assembly including three
glass fibre-reinforced polyester blades.
In the design process, 17 turbines were originally
considered for the site. However, the scheme was
reduced to 14 to ensure that turbines were not sited too
close to High Barn Farm and Manor Farm which are close
to the south eastern boundary of the site and Yelden.
The installed generation capacity of the wind farm will be
36MW which on an annual average will provide some
9MW. The biomass plant will add a further 4MW at
times of low wind power and high electricity demand.
The maximum height from the turbine base to the top of
the blade tip will be 125m when the blades reach their
highest point. The turbine hub height will be up to 80m
with each blade measuring up to 45m. For comparison
the existing site mast is 70m tall.
The turbines would start operating when the wind
speed reaches approximately 4 metres per second and
would reach their maximum rated power output at
around 15.0 metres per second.
The turbines are equipped with lightning protection,
which protects the entire turbine from the tips of the
blades to the foundation. Noise damping is also an
integral part of the turbine design to ensure that noise
emissions are kept within acceptable levels. |
| Wind Farm Construction |
The wind farm will consist of up to 14 turbines and the following associated infrastructure:
- access Roads;
- anemometry mast;
- control building;
- borrow pits (if required), and
- temporary car park and temporary construction compound incorporating laydown area, site office
and concrete bacthing area.
|

|
| Turbine Construction Process |
Typical turbine foundations consist of a 4.8m diameter
reinforced central concrete pedestal, together with a
reinforced concrete slab of around 15.7 x 15.7m (see
diagram below).

The turbine tower will be bolted to the foundation,
with each foundation requiring around 350m3 of
concrete. To ensure a single block of concrete, it is
necessary to pour each foundation in one day.
A temporary “crushed stone” hardstanding area of
approximately 18m x 40m (see diagram below) will be
required at each turbine base for related construction
and crane erection activities.

The estimated on-site construction period for the
development will be 9 - 12 months, including
reinstatement of temporary working areas.
Construction procedures will be carried out in line with
Environment Agency guidelines and best practice
documents regarding management of pollution risk. |
| Transport & Access to Site During Construction |
In conjunction with the delivery of exceptional loads
such as turbine blades, towers and nacelles, an
assessment of the surrounding highways and roads
network is being undertaken to determine the most
appropriate route for delivery of the equipment. |

Click on the image above to enlarge |
Click on the image the the left to enlarge |
|
|
|